Tā mātou mahi

We research important infrastructure issues, advise on policy, provide expert project support, and share data on both upcoming projects and infrastructure performance.

Our work
Mahere Tūāhanga ā-Motu

We're working on a National Infrastructure Plan that will help guide decision-making by both central and local government and give the infrastructure industry more confidence to invest in the people, technology and equipment they need to build more efficiently.

National Infrastructure Plan
Te Rārangi mahi

The National Infrastructure Pipeline provides insights into planned infrastructure projects across New Zealand, giving industry information to help coordinate and plan.

The Pipeline
Te hītori

We're here to transform infrastructure for all New Zealanders. By doing so our goal is to lift the economic performance of Aotearoa and improve the wellbeing of all New Zealanders.

About us
Ngā rongo kōrero
Fields And Residential Growth

Protecting land for infrastructure: How to make good decisions when we aren’t certain about the future

Our current ‘wait and see’ approach when it comes to protecting land for infrastructure often means that valuable infrastructure doesn’t get built.

By the time we need a new school or a better transport route, the right sites for that infrastructure are gone – they’ve got houses built on them.

This research examines how we can manage the impact of rising land prices on infrastructure project delivery. It finds that designation or acquiring land for infrastructure in advance can make it cheaper and easier to build the infrastructure we need, from neighbourhood schools to major public transport routes.

Planning ahead and protecting sites in advance means we can build the infrastructure we need when we need it. Protecting land needed for future infrastructure keeps our options open and can be easily reversed – we can sell the land if it is ultimately not needed.

Key findings

  • This research identifies and tests methods that can potentially be used to determine when advance site protection is warranted in New Zealand. 
  • It models different scenarios using case studies of advance site protection for a small project – a school for a growing suburb – and a large project – a major rail line extension. In each case study, we considered three broad options for acquiring land to build the project: advance purchase, obtaining an option to purchase, and wait and see. These case studies show that: 
    • advance site protection can be beneficial even when it is uncertain when, or if, a project will be built 
    • in some cases, advance site protection may need to occur decades before projects are built 
    • a ‘wait and see’ approach to land acquisition often means that needed infrastructure doesn’t get built 
    • analysing uncertainty is a powerful tool to decision-makers, but more guidance would be needed to put this into practice. 
Protecting land for infrastructure: How to make good decisions when we aren’t certain about the future