Pipeline snapshot for April to June available

PUBLISHED 12 AUGUST 2026

The latest Pipeline snapshot for the April to June period is now available. 

It shows that in the Pipeline, between March 2026 and June 2026:

  • Fully funded initiatives increased by $4.5 billion to $95.8 billion – including $4.9 billion from initiatives progressing to full funding commitment, balanced by initiatives being completed or moving from fully funded to a lower-certainty funding status.
  • The combined value of initiatives with committed funding or a confirmed funding source increased by $3.1 billion to $192.8 billion – reflecting continued progression of initiatives through planning.
  • Total Pipeline value increased by $15.6 billion to $290 billion – driven primarily by the addition of new unfunded initiatives and adjustments to expected costs of existing initiatives, including those in planning and construction.
  • Initiatives under construction remained constant at $71.2 billion – illustrating projects being completed are balanced by new projects starting construction.