The latest Pipeline snapshot for the April to June period is now available.
It shows that in the Pipeline, between March 2026 and June 2026:
- Fully funded initiatives increased by $4.5 billion to $95.8 billion – including $4.9 billion from initiatives progressing to full funding commitment, balanced by initiatives being completed or moving from fully funded to a lower-certainty funding status.
- The combined value of initiatives with committed funding or a confirmed funding source increased by $3.1 billion to $192.8 billion – reflecting continued progression of initiatives through planning.
- Total Pipeline value increased by $15.6 billion to $290 billion – driven primarily by the addition of new unfunded initiatives and adjustments to expected costs of existing initiatives, including those in planning and construction.
- Initiatives under construction remained constant at $71.2 billion – illustrating projects being completed are balanced by new projects starting construction.